End Milestones
In case of an end milestone:
- another milestone cannot depend on the finish of an end milestone because there is no Finish (Release) on a Task Complete message
- the end milestone cannot be dependent on any other milestones
The following table lists the types of dependencies that can be set up between plan task milestones.
Dependency | Effect |
---|---|
Must Start On | The milestone must start on the date/time specified. If it cannot started for some reason (for example, because a previous plan task is late), a jeopardy condition is triggered. |
Finish to Finish | One milestone is able to be released when the other milestone is released |
Start to Finish One | One milestone can be released only when the other begins |