End Milestones

In case of an end milestone:

  • another milestone cannot depend on the finish of an end milestone because there is no Finish (Release) on a Task Complete message
  • the end milestone cannot be dependent on any other milestones

The following table lists the types of dependencies that can be set up between plan task milestones.

Dependency Effect
Must Start On The milestone must start on the date/time specified. If it cannot started for some reason (for example, because a previous plan task is late), a jeopardy condition is triggered.
Finish to Finish One milestone is able to be released when the other milestone is released
Start to Finish One One milestone can be released only when the other begins