Jeopardy Management for Execution Plans

If a given plan task or milestone is in jeopardy, it may or may not indicate that the overall execution plan is in jeopardy. The jeopardy manager also provides facilities for monitoring whether the whole execution plan is running on time, or taking longer to complete than expected. This is done by monitoring the forecast end date and time of the plan and comparing it against several threshold dates.

If you use start date scheduling or end date scheduling for your execution plans, you can set a different set of jeopardy conditions at plan level.