Defining the Business Process in the Provider Project

Rename and configure the business process.

Procedure

  1. Open the Business Process(SPProcessPackage-process) business process.
  2. Relabel it as Service Provider Process.
  3. Select the Start event.
  4. In the General tab of the Properties view, change the Trigger Type to Message.
  5. Select the single task in the process.
  6. In the General tab of the Properties view, change the Activity Type to Script Task.
  7. Change the Label to Set Response.
  8. Save the project.