Reallocating Work Items to the World
The Reallocate to World function is used to reallocate a work item to any available user.
- Procedure
- Select a work item in the work item list that currently has a state of Allocated or Pended.
- Select
Workitem Reallocate
dialog box is displayed, which is used to choose the user to whom you would like to allocate the work item.
. The
Note: You may not be able to see all resources mapped to a particular position because there may be resources mapped to a position that was created in an LDAP container for which you don’t have visibility, (because of an organization relationship). In these cases, you will not see that resource when viewing the position. (This applies only to positions, not to groups.)
For more information, see the "Container Organization Relationships" section in the TIBCO® BPM Enterprise Administration Guide
- From the Version drop-down list, select the version of the organization model that contains the resource you want to allocate the work item to.
- From Organizations, drill down to an organizational entity on the left to which the resource has been mapped.
- Either click
to the right of the resource name in the Resources list or select the resource in the Resources list, then click
on the bottom of the Selected list.
- Optionally select
Revert data.
If you select this option it causes any data that has been entered or modified in the work item before allocating it to revert to its original value. (If any data in the work item has been entered or modified, the work item will have a state of Pended.)
If you decide that you no longer want the work item to be allocated to this user, you can remove them from the Selected list by selecting
.
- Select Reallocate.
The work item appears in the work item list of the resource that you selected, with a state of Allocated.