Post-migration

Updating Adapter Schema References

After successfully migrating Adapter projects created on ActiveMatrix BusinessWorks 5.x or ActiveMatrix BusinessWorks 6.x, complete the post-migration steps.
Note: The post-migration steps are required to replace the adapter schema where referenced to plug-in schema.

If there is a ActiveMatrix BusinessWorks 5.x or 6.x generic activity that uses the PeopleSoft adapter AE schema in ActiveMatrix BusinessWorks 5.x or 6.x projects, then after migration, perform the following steps to fix the ActiveMatrix BusinessWorks 6.x generic activities:

Note: The generic activities currently supported are Start, End, Mapper, Call Process, JMS Queue Sender, and JMS Queue Receiver.

Procedure

  1. Keep the JSON preference file (migrateSchema.json) at root level of project.
  2. Right-click on the project.
  3. Select Refactor > Update Adapter Schema References.
  4. Select the project and click Finish.