Post-migration

Updating Adapter Schema References

After successfully migrating Adapter projects created on ActiveMatrix BusinessWorks 5.x, complete the post-migration steps.
Note: The post-migration steps are required to replace the adapter schema where referenced to plug-in schema.
Note: Post-migration does not support Custom schema used in BusinessWorks 5.x project.

The below ActiveMatrix BusinessWorks 6.x generic activities are supported. For additional activities supported, please refer to the Readme.

  • Start
  • End
  • Mapper
  • Call Process
  • JMS Queue Sender
  • JMS Queue Receiver
  • Parse XML
  • Assign
  • Transitions

If there is an ActiveMatrix BusinessWorks 6.x generic activity that uses the PeopleSoft adapter AE schema in ActiveMatrix BusinessWorks 6.x projects, then after migration, perform the following steps to convert the PeopleSoft adapter AE schema to PeopleSoft plug-in schema for the ActiveMatrix BusinessWorks 6.x generic activities:

Procedure

  1. Keep the JSON preference file (migrateSchema.json) at root level of project.
  2. Right-click on the project.
  3. Select Refactor > Update Adapter Schema References.
  4. Select the project and click Finish.