Migrating projects from Adapter to Plug-in

You can migrate ActiveMatrix Adapter for PeopleSoft projects created in TIBCO Designer™ to ActiveMatrix BusinessWorks Plug-in for PeopleSoft in the following manner.

Note: Before migration, back up the original TIBCO ActiveMatrix BusinessWorks™ 5.x projects.
    Procedure
  1. Start TIBCO Business Studio.
  2. Click the Project tab and select Migrate BW Projects.
  3. In the Project Migration Wizard, click Browse in the Select Project(s) to be Migrated field and select the project you want to migrate.
    The default selection is Migrate Single BusinessWorks 5.x Project. Click Migrate Multiple BusinessWorks 5.x Projects to migrate multiple 5.x projects.
  4. Click Migrate Project > Start Migration. After the migration is complete, click Finish.
  5. Finally, perform the Post-migration steps to correct the schema.