Migrating projects with Respond to Adapter Request Activity

You can migrate your projects that use the Respond to Adapter Request activity from ActiveEnterprise Adapter Palette to Reply from RFC/BAPI in SAP activity in TIBCO ActiveMatrix BusinessWorks™ Plug-in for SAP Solutions in the following manner

Procedure

  1. In TIBCO Business Studio™ for BusinessWorks™, right-click on the project in the Project Explorer and select Refactor > Migrate Adapter to Plug-in.
  2. In the Migrate Adapter Activities window, select the project to migrate. Review the processes that are displayed for migration and then click OK.
  3. Open the processes and realign the mapper activity if required. Add mappings in the mapper activity.
    Note: If the schema for one RFC/BAPI activity is refreshed, then the other RFC/BAPI activities in the same process that using are using the same schema may not be refreshed.

    All the configurations of the Respond to Adapter Request activity is migrated to respective fields of Reply from RFC/BAPI in SAP activity under General and Advanced tab.

    Note: In the migrated activity, the fields not present in the Respond to Adapter Request activity, but are present in the Reply from RFC/BAPI activity will have default values. Some of these fields can be configured through JSON preference file. For more information, see Working with Preference File (JSON) for migration.
  4. To run the migrated project, from the menu bar click Run > Debug Configurations.
  5. In the Debug Configurations windows, click Debug.