Migrating projects with Publish to Adapter activity and Subscription Service

You can migrate your projects that use the Publish to Adapter from ActiveEnterprise Adapter palette and Subscription Service in TIBCO ActiveMatrix® Adapter for SAP to IDoc Reader or JMS Send Message Activity in TIBCO ActiveMatrix BusinessWorks™ Plug-in for SAP Solutions in the following manner:

Procedure

  1. Start TIBCO Business Studio.
  2. Click Project tab and select Migrate BW Projects.
  3. In the Project Migration Wizard, the default selection is Migrate Single BusinessWorks 5.x Project in the Migration Project Type section. Click Migrate Multiple BusinessWorks 5.x Projects to migrate multiple 5.x projects.
  4. In the Select Project Location section, click Browse in the Select Project(s) to be Migrated field and select the project you want to migrate.
  5. Click Migrate Project > Start Migration. After the migration is complete, click Finish.
    All the migrated projects are displayed in the Project Explorer view at the parent level.
    All the schemas defined under AESchemas folder of the TIBCO ActiveMatrix BusinessWorks 5.x project do not get migrated. In the Configuration tab of the Publish to Adapter activity in TIBCO ActiveMatrix® Adapter for SAP, an Adapter Service should be mentioned for migration. Only the schema that is referenced by the Publish to Adapter activity is re-fetched during migration.
    Note: This release of TIBCO ActiveMatrix BusinessWorks™ Plug-in for SAP Solutions does not support migration of RequestReply and Custom AESchema.

    All the configurations of the Subscription service is migrated to respective fields of IDoc Reader or JMS Send Message activity under General and Advanced tab. In the General tab of the migrated activity, the migrated shared resource will be mapped to shared resource field. The schema selected in the Subscription service is mapped to IDoc Name of the migrated activity. The destination of these activities is the same for both and it refers to the destination in the Transport tab of the subscription service in TIBCO ActiveMatrix® Adapter for SAP.

    In the migrated activity, the fields that are not present in the Subscription Service but are present in the IDoc Reader activity will have default values. After migration, you need to manually provide the values for the Confirm IDoc Destination field in the Advanced tab of the IDoc Reader activity. This is required when the IDoc Confirmation check box is selected in the IDoc Reader activity. Also, the IDoc Error Destination field in the Advanced tab of the IDoc Reader activity.

    Note:
    • In the migrated activity, the fields that are not present in the Subscription Service but are present in the IDoc Reader will have default values. These fields can be configured through JSON preference file. For more information, see Working with Preference File (JSON) for migration.
    • After migration, the JMS send activity must be recreated with IDoc Schema input as they have different schema structures for ActiveMatrix BusinessWorks 5.x adapter and ActiveMatrix BusinessWorks 6.x plug-in activities.
  6. To run the migrated project, from the menu bar click Run > Debug Configurations.
    A default JMS connection is created after migration if the TIBCO ActiveMatrix® Adapter for SAP project does not have any JMS connection resource.

    If a JMS connection is present, it is migrated. If there are multiple Adapter Subscriber activities or Publish to Adapter AE activities with using different transports, then value of JMS properties overwrite the last process created. If the JSON preference file is present the value from JSON file is used.

    If the Transport tab has JNDI look ups and the SSL configurations enabled, a JNDI connection will be created and the SSL configuration is migrated.