Running the Project

To run the project for the Parent child Integration component of the Invoke Business Service activity process, perform the following steps:

Procedure

  1. In the Project Explorer view, expand the Processes > invoke_business_service resource, and then double-click Invoke_BS_ParentChild.bwp.
  2. Click Run > Debug Configurations...
    The Debug Configurations dialog opens.
  3. Expand the BusinessWorks Application option and select BWApplication.
  4. In the Applications tab, all processes will be selected. Click the Deselect All button and select the invoke_business_service.Invoke_BS_ParentChild.bwp option.
  5. Click the Apply button and click the Debug button.
  6. Click Debug to run the process.
  7. Click the icon to stop the process.