Migrating Projects With Adapter Request-Response Server Activity and Request-Response Invocation Service

You can migrate your projects that use the Adapter Request-Response Server Activity of from ActiveEnterprise Adapter palette and Request-Response Invocation Service of TIBCO ActiveMatrix® Adapter for Siebel to Event Invocation Activity in TIBCO ActiveMatrix BusinessWorks™ Plug-in for Siebel.

Procedure

  1. Perform step 1 to step 3 of Migrating Projects from Adapter to Plug-in.
    All the schemas defined under AESchemas folder of the TIBCO ActiveMatrix BusinessWorks 6.x project are not migrated. In the Configuration tab of the Adapter Request-Response Server Activity in TIBCO ActiveMatrix® Adapter for Siebel, an Adapter Service must be mentioned for migration.

    Only the schema that is referenced by the Adapter Request-Response Server Activity is fetched during migration. While migrating the project schema is fetched from server and stored in Siebel Object Editor. All the required configurations of the Adapter Request-Response Server Activity and Request Response Invocation Adapter Service is migrated to respective fields of BW6 Siebel plugin activity under the General tab.

    In the General tab of the migrated Siebel plugin activity, the migrated shared resource is mapped to the shared resource field. The schema selected in the Invoke an Adapter Request Response Service activity is mapped to Siebel Object Reference of the migrated Siebel activity.

  2. To run the migrated project, click Run > Debug Configurations from the menu bar.
  3. In the Debug Configurations window, click Debug.