Example - Basic Costing

Top  Previous  Next

This example demonstrates a process of dealing with invoices within a company and the associated costs.

 

The cost values on display are activity duration and activity cost. The cost display on each activity display the activity duration and the cost of the activity.

 

 

 

 

The total cost of this example process is £237.50 and the total duration is 17hrs 30mins. This will be displayed on the Basic Costing panel (to display the Basic Costing panel, from the View menu choose Toolbars and Panels. Select the Panels tab and select the Basic Costing Panel check box).