Seismic Datum Adjustments

If the source project has a SRD (Seismic Reference Datum) that is different from the Petrel SRD then the following data types will be shifted during import:

In order to know how much to shift the time values by you are prompted to supply a replacement velocity. This should be the linear average velocity for the interval between the two SRDs.

 

A default replacement velocity can be specified in the Match Merge Option settings. The default value will be used and the replacement velocity window will not appear during import.