Reassign activity IDs

Top  Previous  Next

Activity IDs can be automatically reassigned, for example if activities have been moved to a new position in a diagram, or if activities have been added/removed.

 

Note: If the IDs are not being reassigned correctly then check the alignment of the activities. For example, if an activity on the top line is above the other activities then the operation will assume this is the first activity and assign it ID 1, regardless of the order. For more information on aligning activities see Aligning Objects.

 


 

1.From the Diagram menu choose Reset ID Numbers.

 

2.From the Reset ID Numbers panel choose the direction of the resetting.

 

3.From the Scope panel choose the scope of diagrams to apply the ID resetting to.