Rolling up statement links

Top  Previous  Next

Activity statement links can be automatically rolled up and copied to all parent activities from child activities.

 

Note: This operation cannot be undone once completed.

 

 

 

 

 


 

 

1.From the Tools menu choose Statement Links, then Rollup Statement Links.

 

2.Select one of the following options:

 

Rollup to the current diagram

This will copy all statement links from child activities to all parent activities up to the diagram that you are currently viewing.

 

Rollup to the level 1 diagram

This will copy all statement links from child activities to all parent activities up to the level 1 diagram.

 

3.Click OK.

 

 

Running the process from the command line

The process can be run from the command line through the use of a Control Script File (.csf). Note: This method will always roll up statements to the level 1 diagram. Any issues will be reported in a log file, which is created in the same location as the CSF file.

 

Example

 

C:\TIBCO Nimbus\Client\Ctrl.exe "E:\TIBCO Nimbus\Process Repository" "C:\StatementRollup.csf"

 

What is a Control Script File?

 

 

Related Topics:

 


 

Creating statement links