Unpackage a statement set

Top  Previous  Next

Statement sets can be packaged to include all statement records, file attachments and data table records and then transferred to another process repository. If you want to transfer a process map and its linked statements then you first have to transfer the appropriate statement sets before transferring the process map (i.e. unpack the statement sets before unpacking the process map).

 

Note: Linked file attachments are stored in the Process RespositoryATTACH folder.

 


 

1.From the Tools menu choose Statement Sets.
2.Click the statement set to highlight it.
3.From the File menu choose Unpack.

4.    Choose one of the following options and click OK:

 

Internal backup or transfer should be selected if the content is only for re-use or for an internal backup. All personal information will be maintained. This option should not be selected if you intend the content to be transferred to a third party as doing so will breach data-privacy regulations.

Received from TIBCO Nimbus for support purposes should be selected if the content was originally sent from your company and received back from Nimbus®. All personal information will be maintained. Do not select this option if you are not certain of the origin of the content.

Received from an external company or organization should be selected if the content has been received from an external company or organization. All personal information will be removed from the content.

Unknown should be selected if the source of the content is unknown. All personal information will be removed from the content.

 

Related Topics:


Package a statement set

Comparing statement sets