Deploying the Business Process Application

The ActiveMatrix BPM application is deployed via TIBCO Business Studio BPM Edition in the usual way.

Procedure

  1. In TIBCO Business Studio Deployment Servers view, right-click the server, and select Deploy Module.
  2. In the Select Module Type dialog, select Deploy BPM Project and click Next.
  3. In the Select Project dialog, select the project AdvBEIntegration and then click Next.
  4. Accept the defaults in the Administrator Setup dialog and click Next.
  5. In the Property Configuration dialog, override the outbound HTTP property to select the existing resource instance AdvBEIntegrationClient.
  6. Click Finish to deploy the application.

    You have completed creating and deploying the TIBCO ActiveMatrix BPM application. Proceed to the next section to create a Business Events application.